Parish Council demolishes Winchfield new town plan

Figure 6 Winchfield New Town Summary of Key Findings

Winchfield new town area not suitable for large scale development

The Parish Council have demolished plans for the proposed Winchfield new town in their submission to the Hart Local Plan Regulation 19 consultation. The have produced a 690-page report that can be found here. Their main conclusions about Policy SS3 that calls for the new town to be built in the area of search are (our emphasis):

Our review of the available technical evidence, with STR005 released only through a FOI request, demonstrates the highly constrained nature of the AoS, and the significant environmental and infrastructure issues that need to be overcome. A Site Appraisal prepared by Michelle Bolger Expert Landscape Consultancy is provided and this demonstrates that the AoS is significantly constrained and concludes that little land exists within the AoS which could be considered suitable for large scale residential development. We flag up the complete failure of the Draft Plan to identify the key infrastructure necessary for the provision of a new settlement, or indicate how it will be provided, by whom and when. Given the complete lack of any detailed evidence demonstrating that a new settlement is either deliverable or viable, we do not see how provision can be made for it within the Draft Plan.

Winchfield New Town Expert Evidence

The expert evidence from Michelle Bolger is a joy to behold. Her much shorter report can be downloaded from the link below, together with the appendix that contains the wonderful graphics depicting all of the constraints on the area of search.

The final summary is shown on the image above. This summarises the findings of the whole report in relation to the various sites that have been put forward, concluding (emphasis mine):

All of the sites are significantly constrained and the vast majority of the area of search (AoS) south of the M3/Railway is considered to be unsuitable for large scale development (i.e. it would cause severe landscape harm that would be difficult to remedy or mitigate)…

Land within the north-western parts of the AoS…are also significantly constrained. Development here could not occur without harm to the local countryside character and this would also impact upon the character and enjoyment of the Public Right of Way network. Development may also result in visual coalescence between Hartley Wintney and Hook.

Overall this appraisal finds that the AoS identifies a landscape that is highly unsuitable for large scale residential development. The new settlement envisaged by draft policy SS3 would result in significant landscape and visual harm and be at risk of harming components within the landscape which hold high landscape, amenity, ecological and heritage value.

The build up to the final conclusion starts with the area of search:

Figure 1 Winchfield New Town Area of Search and Context

Figure 1 Winchfield new town Area of Search and Context

It then goes on to show Hart’s own landscape capacity study which shows that most of the area has low or low/medium capacity. The only area with medium/high capacity is the proposed Elvetham Chase (Pale Lane) site and it’s westward extension towards Winchfield. The Murrell Green area is shown as Medium capacity. However, this was decided before the Major Accident Hazard gas pipeline was discovered by Hart Council.

Figure 2 Winchfield New Town Landscape Capacity Study

Figure 2 Winchfield Landscape Capacity Study

The paper then goes on to identify the constraints in the area of search, starting with areas designated as SSSI’s, SINCs, tree preservation orders, ancient woodland, and listed buildings.

Figure 3 Winchfield New Town Key Constraints Designations

Figure 3 Winchfield New Town Key Constraints Designations

Then other constraints such as visual sensitivity, flooding, footpaths, unavailable land, landfill, narrow bridges, high voltage transmission lines and the gas pipeline are added:

Figure 4 Winchfield New Town Key Constraints Assessment

Figure 4 Winchfield Key Constraints Assessment

Then all of the constraints are brought together on one diagram, showing just how little land exists within the AoS that could be considered suitable for large scale residential development.

Figure 5 Winchfield New Town Key Constraints Composite

Figure 5 Winchfield Key Constraints Composite

 

All of this report is drawn from pre-existing material. One wonders why Hart Council is continuing to promote such a daft idea. Certainly, £50K is not going to cover costs of putting together a robust Winchfield new town master-plan to fulfill all of their magical promises to turn horses into unicorns. We shall see what the inspector makes of this.

The report and appendix can be downloaded here:

Winchfield Site Appraisal
Winchfield Site Appraisal
Winchfield Site Appraisal Appendix
Winchfield Site Appraisal Appendix

 

Posted in Hart District Council, Hart Local Plan Examination, We Heart Hart Campaign, We Love Hart Campaign and tagged , , , , , , , .