Shapley Heath Baseline Studies Fall Short of Cabinet Claims

In their defence of the Shapley Heath project debacle, Hart Cabinet have made a great deal of noise about the Baseline Studies produced by the developers as part of the project. The purpose of this post is to analyse the conclusions of those reports and come to a conclusion about their value.

The first point to note is that those reports have now been removed from Hart’s website. However, we did download them when they were available. Together they take up hundreds of MB of disk space. We have made them available here, on our Google drive for those who may wish to view them.

Summary of Results of the Shapley Heath Baseline Studies

Geo-Enviro Study

Low risk from past use, but calls for more detailed work. Glosses over landfill at Scotland Farm and Beggars Corner.

Transport

Proposes an impractical technocratic nirvana of bicycles, cargo-bikes and e-scooters with convoluted car journeys; Council should only consider “increases in highway capacity as a last resort”. Great way to wriggle out of infrastructure spending.

Landscape

Hundreds of pages of bumph, many simply repeating earlier studies in a massive appendix,  resulting in no conclusions except for a call for further work to “consider landscape value, sensitivity and capacity”.  In effect, totally useless.

Agricultural Land Classification

No specific report produced. One chart in the Landscape report. Was supposed to be extended into a detailed study, but apparently not produced.

Archaeological and Heritage

Concedes there would be harm to heritage assets, but claims “informed masterplanning” would avoid or reduce harm. More detailed work required.

Flooding and Drainage

Study concludes that there is a risk of fluvial (river), surface, reservoir and groundwater flooding across parts of the Area of Search. Recommends further work, particularly groundwater monitoring. Some pieces of evidence contradictory. Recommends areas prone to flood as “dry routes” out of the site.

Water Cycle/Management

No report produced.

Utilities

No report produced. It seems they’re ignoring the high pressure gas main and the high-voltage power lines.

Air Quality

Study admits the M3 is the biggest air quality constraint and that nearby SSSIs could be at risk. Apparently, air quality issues during the 16-year build phase are only temporary, so we don’t need to worry about them. Thankfully, they appear to have dropped the idea of building a tree-burning power plant.

Noise

Flawed study didn’t take account of increased traffic levels arising from the development. Admitted to needing an 80m buffer zone either side of the M3 and 20m from the A30 London Road. Concludes that “there are no planning or technical reasons with regard to noise to refuse the promotion of this site as a residential development”.

Contamination

No specific report produced

Ecology & Biodiversity Net Gain

Fairly useless report that documents the different habitat groups in the Area of Search and attributes biodiversity points to each one. Concludes with a statement of the bleeding obvious that to achieve a biodiversity net gain, there needs to be an increase in biodiversity. However, replacing any of the cropland or grassland with urban areas will automatically reduce biodiversity.

Ancient Woodland, Ancient and Veteran Trees

Useful report detailing all of the areas of ancient woodland and a schedule of 37 veteran trees. The report points out that development that might damage these areas be refused. It recommends buffer zones around the veteran trees of around 5m from the edge of the canopy and 15m from the ancient woodland.

Overall Status of Shapley Heath Baseline Studies

The Opportunity Board that took place in March 2021 promised no less than 14 Baseline Studies and showed the status of each at that time.

Status of Shapley Heath Baseline Studies as of March 2021

Status of Shapley Heath Baseline Studies as of March 2021

Despite claims by Cabinet that 10 studies have been produced, only 9 were published. However, one of them covered both Flood Risk and Drainage, so maybe we can say 10 of the promised subject areas were covered. It remains to be seen what happened to the other four.

Status of Shapley Heath Baseline Studies Falls Short of Expectations

Status of Shapley Heath Baseline Studies Falls Short of Expectations

Interestingly, Community Campaign Hart have gone on record saying the have not read the documents. So, obviously they are total experts on the content of the reports and are well placed to judge their value 😉.

Questions about Shapley Heath Baseline Studies to CCH

Questions about Shapley Heath Baseline Studies to CCH

Answers about Shapley Heath Baseline Studies from CCH

Answers about Shapley Heath Baseline Studies from CCH.

Now let’s go through the details of each report.

Topographical and Ground Survey aka Geo-Enviro Desk Study

This was published as the Geo-Enviro desk study. The document was produced by Wardell Armstrong and is dated January 2021, despite the March status report showing no work had started. Note this is a desk based study; no actual field work has been carried out.

Geo-Enviro Study Objectives Wardell-Armstrong

Geo-Enviro Study Objectives.

They conclude that “site is considered to present an overall low risk from past use” and “the site is suitable for the proposed end use of residential and or commercial development with associated infrastructure”.

Geo-Enviro Study Low Risk from Past Use Wardell-Armstrong

Geo-Enviro Study Low Risk from Past Use

However, they go on to caveat their conclusions by stating that more detailed geotechnical work is required about the appropriate foundation solution for parts of the site.

Geo-Enviro Study Potential contamination Geotechnical Assessment Wardell-Armstrong

Geo-Enviro Study Potential contamination Geotechnical Assessment

In the body of the paper they do note that Beggars Corner and Scotland Farm are former landfill sites, but gloss over the implications of this.

Geo-Enviro Study Potential Historic Landfill Beggars Corner Scotland Farm Wardell-Armstrong

Geo-Enviro Study Potential Historic Landfill Beggars Corner Scotland Farm

They also go on to note in their terms and conditions that they offer no guarantee  or warranty on their findings.

Geo-Enviro Study Potential No Guarantee or Warranty Wardell-Armstrong

Geo-Enviro Study Potential No Guarantee or Warranty

Shapley Heath Baseline Studies – Transport

Summary

The Transport Studies consist on seven “Topic Papers” delivered via email from the Steer Group. They are a triumph of technocratic idealism over common sense.

In their nirvana, everyone will ride bicycles or e-scooters so there’s no need to make a significant investment in roads.  The Council should abandon the philosophy of “Predict and Provide” and in favour of “Decide and Provide”, or rather don’t provide. They elaborate on this saying “user hierarchy putting pedestrians and cyclists first and motor traffic last, and design features including limited and well-placed car parking”.

This means that the Council should:

  • Simply “decide” the “preferred future” and provide for that future instead. SO, they can decide not to provide proper road infrastructure.
  • Actively seek to add “convoluted car journeys”.
  • Not try to predict the future traffic flows arising from 5-10,000 additional houses.
  • Only be “considering increases in highway capacity as a last resort”.
  • Include only limited parking facilities.
  • Assume everyone is going to cycle or take their lives in their hands on an e-scooter, instead of driving to do their big shop at the supermarket.
  • Not bother working out the costs of transport improvements.

In other words, they have decided that they will aim for an impractical technocratic nirvana so there’s no need to cost out a practical solution.

More Walking and Cycling Routes Plus Cargo Cycles

The aims of providing more walking and cycling routes are laudable. The roads around the proposed site notably lack pavements in  most places and there are almost no dedicated cycle paths.  However, there are some completely ridiculous ideas such as “freight to be transported by cargo cycles”. I don’t think any new supermarket would be happy to be restocked by a fleet of “cargo cycles”.

Shapley Heath Transport Study e-cargo bikes

Shapley Heath Transport Study e-cargo bikes

Convoluted Car Journeys

They also propose to “create more convoluted journeys for private vehicles thereby reducing propensity for short distance car trips”. In other words design the environment so it is difficult for cars to get in, through and out of the new development. This is a recipe for more congestion and poor quality of life. It is fundamental to economic efficiency and vibrant social life that it is easy for people to go where they want, when they want. The thing about private cars is that they promote freedom of movement and convenience. They seem to want to “Decide” that new residents should live the lives of Trappist Monks, never leaving the new town and not having visitors.

Shapley Heath Transport Study e-scooters and convoluted car journeys

Shapley Heath Transport Study e-scooters and convoluted car journeys

Better Public Transport

They also call for more busses. However, if the No. 7 bus service that already goes through Hartley Wintney is any guide, there is precious little demand for this mode of transport. By observation, these busses often have no passengers at all, and never more than a handful. It is difficult to see how this will change even with 5-10,000 extra houses.

The papers also call for more train journeys. However, they acknowledge that pre-pandemic the line was operating at maximum capacity. They outline a series of improvements that are planned for the Wessex line. However, it isn’t clear whether any of them will improve capacity or enhance services from Winchfield.

Ignoring EVs Eliminate Tail Pipe Emissions

Part of their rationale for strongly discouraging car use is to cut tail-pipe emissions. They fail to understand that by 2030 all new cars sold will be EVs, with no tailpipe emissions. Even now, hybrids are taking an ever increasing share of the market, so CO2 emissions are already falling in urban areas. It can be seen that their  rationale for reducing car usage  completely falls away.

No Costing

None of the Topic Papers addresses the costs of even providing footpaths and cycle paths. Of course they don’t address the cost of road improvements because they should only be “considering increases in highway capacity as a last resort”. In other words, they have decided that they will aim for an impractical technocratic nirvana so there’s no need to cost out a practical solution.

Landscape Character Assessment

The Environmental Dimension Partnership (EDP) have produced hundreds of pages of bumph resulting in no conclusions. Much of the report is a massive appendix of earlier work carried out for the Council. They conclude by calling for further work to “consider landscape value, sensitivity and capacity”.  In effect, totally useless. The work is nowhere near as good as the work carried out by Michelle Bolger on behalf of Winchfield Parish Council.

Shapley Heath Landscape Study Further work required

Shapley Heath Landscape Study Further work required

Archaeological and Heritage Study

This is an 87-page report produced again by EDP. The report concedes that heritage assets would suffer “harm” as a result of such a significant development. However, they contend that with “informed masterplanning, it may be possible to avoid or reduce harmful effects”. Note the “may”.

Shapley Heath Archaeological and Heritage Study

Shapley Heath Archaeological and Heritage Study – Harm to heritage assets

Of course, they say more work is required, including actually visiting the site! Got to keep those consultancy fees rolling in.

Shapley Heath Baseline Studies – Flooding and Drainage

The Flooding and Drainage studies were produced as one document by Wardell-Armstrong who also produced the ge0-enviro desk study. This is an 68-page document plus three appendices. One plus point is that the various flood events documented on this website are incorporated into the evidence base.

 

The main document shows that there is a risk of fluvial (river), reservoir, surface water and groundwater flooding across large parts of the site. It recommends further work to better quantify the risks and work out the mitigation.

Shapley Heath Flood Risk Study Additional Work Programme

Shapley Heath Flood Risk Study Additional Work Programme

In particular, a 12-month borehole study is recommended.

Shapley Heath Flood Risk Study 12 month borehole study required

Shapley Heath Flood Risk Study 12 month borehole study required

Given the project has been cancelled and no budget is currently allocated, it isn’t clear when or if this work will take place.

It is worth noting that significant parts of the evidence base are self-contradictory.

Surface Water Contradictions

The first point to note is that they provide a very low quality image of the parts of the Area of Search that are subject to surface water risk.

Shapley Heath Flood Risk Study Figure 10 Surface Water

Shapley Heath Flood Risk Study Figure 10 Surface Water

At first glance, it looks like pretty much the whole site is clear of surface water flood risk.

However, if you superimpose the Area of Search on Hart’s own map of surface water flood risk, a very different picture emerges.

Shapley Heath Surface Water Flood Risk from Hart Council Maps

Shapley Heath Surface Water Flood Risk from Hart Council Maps

Large swathes of the Area of Search is subject to surface water flood risk. An addendum to Hart’s own Strategic Flood Risk Assessment states that their various models of surface water flood risk underestimate the extent of flooding.

Models Underestimate Surface Water Flood Risk

Models Underestimate Surface Water Flood Risk

Clearly, more work is required on this subject.

Groundwater Contradictions

They use two different charts to illustrate the risk of groundwater flooding. The first shows high risk to the North East of the site and negligible risk across the central belt.

Shapley Heath Flood Risk Study Figure 11 Groundwater Flood Risk

Shapley Heath Flood Risk Study Figure 11 Groundwater Flood Risk

The second map shows high risk to the south, medium risk in the north east and low (note not negligible) across most of the rest of the site.

Shapley Heath Flood Risk Study Figure 12 Groundwater Flood Risk

Shapley Heath Flood Risk Study Figure 12 Groundwater Flood Risk

No wonder they called for the 12 month borehole study to work out what the real risks are.

Exit Route contradictions

As part of their mitigation strategy, they identify a number of “dry routes” out of the site. These include Taplins Farm Lane, Station Road, Bagwell Lane and Totters Lane. The very roads that we have documented flood frequently and often to such an extent that they are impassable. They even reproduced the graphic below in their own document.

Shapley Heath Flood Risk Study Allegedly Dry Routes

Shapley Heath Flood Risk Study Allegedly Dry Routes

Winchfield, Hook, Crookham Village Floods 3 January 2016

Winchfield, Hook, Crookham Village Floods 3 January 2016

Clearly, they need to think again.

Shapley Heath Baseline Studies – Air Quality

Wardell-Armstrong have produced another 15-page report. However, the report is next to useless because there are no monitoring stations within the boundary of the Area of Search.

They do have a section on potential air quality impacts. They dismiss concerns about any impacts during construction as only “temporary.

Shapley Heath Air Quality Study Temporary Impacts during 16 year construction phase

Shapley Heath Air Quality Study Temporary Impacts during 16 year construction phase

However, the bid documentation suggested a building trajectory of 16 years. This hardly fits most people’s definition of temporary.

Shapley Heath Housing Trajectory Sept 2020

Shapley Heath Housing Trajectory Sept 2020

They then move on to the “operation” phase, by which they mean the impact on air quality having built 5-10,000 extra houses.

They concede that there could be potential damage to nearby SSSI’s, although they do not mention the many SINCs within the Area of Search.

Shapley Heath Air Quality Study Potential Damage to SSSIs during operation

Shapley Heath Air Quality Study Potential Damage to SSSIs during operation

They also admit that the M3 is “the most notable constraint” regarding air quality.

Shapley Heath Air Quality - M3 Is A Significant Constraint

Shapley Heath Air Quality – M3 Is A Significant Constraint

Thankfully, they have given up on the idea of a tree-burning biomass power plant or CHP as they euphemistically call it. In a previous Sustainability Appraisal they used the potential of such a plant to rank Shapley Heath above other options. Heaven knows why, burning wood to produce power generates more CO2 and noxious particulate emissions than burning coal.

Shapley Heath Air Quality - Given up on idea of a Power Plant

Shapley Heath Air Quality – Given up on idea of a Power Plant

Of course they need to do further more detailed work.

Shapley Heath Baseline Studies – Noise

Our friends at Wardell Armstrong have been busy again, this time on a 39-page Noise Assessment report. However, we believe this assessment to contain a very significant flaws:

  1. Study Timing.
  2. No account was taken of the extra traffic generated by the development.
  3. They assumed the development would be residential only.

Study Timing

First, the study was carried out in mid-June 2021. They assumed traffic levels were back to normal levels. However, some Covid restrictions were still in place up to mid-July 2021.

Shapley Heath Noise Study - Study period 9-14 June 2021

Shapley Heath Noise Study – Study period 9-14 June 2021

In addition, the study period was 9-14th June 2021. The 12th of June was a Saturday and the 13th was a Sunday. Weekends generally have lower traffic levels, so some of the readings they took will understate the mid-week noise levels.

Extra Traffic Ignored

The extra traffic that will be generated by the development was not considered in their work. They justify this by saying traffic volumes would have to double to generate a 3dB increase in noise levels.

Shapley Heath Noise Study - Will Not Consider Impact of Proposed Development

Shapley Heath Noise Study – Will Not Consider Impact of Proposed Development

For a road like the M3, that is justifiable. For the A30 London Road, that assumption is at least debatable as it is likely to be one of the major access points should the development go ahead. Therefore, traffic volumes will likely rise significantly. However, for the more minor roads such as the B3016, Station Road, Bagwell Lane and Taplins Farm Lane, this assumption is demonstrably false. There’s currently only a couple of hundred dwellings in Winchfield. Increasing that by 5-10,000 would likely increase traffic on these minor roads by at least an order of magnitude, far more than double. Yet, they have chosen to ignore this obvious fact, despite designing the place to have “convoluted” car journeys adding to congestion and noise.

Assumed Residential Only

Moreover, they also assume that the development would be residential only. However, Hart’s own Project Overview document made it clear that the development would be mixed use, with various employment sites, supermarkets/retail and schools. These types of development will add further to the noise problem.

Shapley Heath Project Overview - Mixed Use Community with Employment and Retail premises

Shapley Heath Project Overview – Mixed Use Community with Employment and Retail premises

Noise Mitigation Strategy

To mitigate the impact they recommend buffer zones around various roads and the railway. These include 80m from the M3, 20m from the A30 and 30m from the railway. We suspect the 10m buffer recommended around the B3016 will prove to be inadequate because traffic levels will rise very significantly.

Shapley Heath Noise Study - Road and Rail Buffer Zones

Shapley Heath Noise Study – Road and Rail Buffer Zones

However, as highlighted above, they have assumed zero extra traffic impact on Station Road, Bagwell Lane and Taplins Farm Lane. Therefore additional buffer zones maybe required. Such a buffer zone would reduce the land available for building, particularly on the parcel of land bounded by the B3016, the M3, Taplins Farm Lane and the railway.

They also recommend various other mitigation strategies such as 2m high fences, special glass in some windows near the major noise sources and “acoustic ventilation” so there’s no need to open windows.

The report concludes that if appropriate mitigation measures are put in place, “there are no planning or technical
reasons with regard to noise to refuse the promotion of this site as a residential development”. Of course, more detailed acoustic design will be required, to generate even more fees.

Shapley Heath Baseline Studies – Ecology and Biodiversity Net Gain

This is a 15-page report plus a 12-page appendix consisting mostly of maps. It was produced by a Ethos Environmental Planning. Overall it’s a chocolate teapot of a report because it concludes that in order to increase biodiversity, the number of biodiversity points need to increase, but it doesn’t say how.

Methodology

It starts by classifying different parts of the Area of Search into Habitat Groups

Shapley Heath Ecology and Biodiversity Habitat Groups

Shapley Heath Ecology and Biodiversity Habitat Groups

It then goes on to award “Biodiversity Units” to each group.

Shapley Heath Ecology and Biodiversity Units

Shapley Heath Ecology and Biodiversity Units

Biodiversity units are calculated using the Biodiversity Metric 2.0. The metric subjects the area of the habitats to a selection of multipliers which determine an areas biodiversity value. The multipliers are the condition of the habitat, its distinctiveness, its connectivity and its strategic significance. However, the report doesn’t explain how they assigned values to the various multipliers. They do caveat their results by making clear that the Biodiversity Metric 2.0 they used is a beta-test trial and the results maybe subject to change.

They go on to say that to enhance or maintain biodiversity, they need to retain high value areas and poorer areas “be targeted for removal”.

Shapley Heath Ecology and Biodiversity target areas for removal

Shapley Heath Ecology and Biodiversity target areas for removal

So, if you already live in the Area of Search, they’re going to target your house for removal.

Conclusions

They conclude with a statement of the obvious. To increase biodiversity points, you have to increase biodiversity points.  However, they offer no advice on how to do that. By combining their tables we have been able to demonstrate that replacing any of the grassland or cropland with urban development, biodiversity will be reduced. This is because the average biodiversity units per hectare are lowest for urban areas.

Shapley Heath Ecology and Biodiversity Points per Hectare

Shapley Heath Ecology and Biodiversity Points per Hectare

This is contrary to the expectations set in the Project Overview:

Shapley Heath Project Overview BioDiversity Net Gain

Shapley Heath Project Overview BioDiversity Net Gain

The Shapley Heath survey last year even suggested that “green spaces within garden communities are also opportunities to enhance biodiversity and the natural environment”. It isn’t clear how they came to that conclusion on the basis of their own survey.

Ancient Woodland, Ancient and Veteran Trees

This is a 39-page report with an 8-page appendix again produced by EDP. Overall, this is a useful report detailing all of the areas of ancient woodland and a schedule of 37 veteran trees. The report points out that the NPPF says that development which might damage these areas be refused, unless there are exceptional circumstances. It recommends buffer zones around the veteran trees of around 5m from the edge of the canopy and 15m from the ancient woodland. Note the results of the survey expire two years after it was conducted. This means that the survey will be useless after December 2022.

 

 

 

 

 

 

Shapley Heath Major Road Transport Issues

Shapley Heath Major Road Transport Issues: Eastbound travel perhaps requires new road

Shapley Heath Major Road Transport Issues: Eastbound travel perhaps requires new road

We first raised issues about the Shapley Heath sustainable transport goals here. That post focused on the minor roads within the area of search. This post examines the major road network surrounding the proposed new development and the gaps in the network. The Shapley Heath Survey has a number of questions about “sustainable transport”. Interestingly, there’s not even an option to request improvement to local roads or to rail services.  When many people think of sustainable transport they think of walking, running and cycling. This can be for fitness, leisure, work or even light shopping.  So, it is worth exploring whether the road network in and around the area of search is capable of delivering the basics such as pavements and cycle paths.

The conclusion for the major roads is that significant investment will be required to alleviate congestion and provide adequate pavements and cycle paths.  Here is the overall assessment, followed by an examination of each road one by one.

Shapley Heath Major Road Issues - Overall Assessment

Shapley Heath Major Road Issues – Overall Assessment

Having read the rest of this article, you might like to respond to the Shapley Heath survey. This is your chance to make known your concerns about the proposals. We have produced a handy guide with suggestions as to how you might choose to answer the freeform questions. The guide can be found on the download below. The full survey can be found here. The survey closes on 5 July.

Shapley Heath Survey with Suggested Responses
Shapley Heath Survey with Suggested Responses

Eastbound Travel

Starting with the those people who might want to travel to Crookham Village, Church Crookham, Fleet or further afield to Farnham, Farnborough or Guildford. We have already established that Chatter Alley, which is only single lane in places with no cycle path or pavement is totally unsuitable for a massive influx of new cars and people. Similarly, Pale Lane is too narrow. So, that raises the possibility of a new road from the eastern tip of the area of search to Hitches Lane. This would help access to Fleet and the Crookhams. This is shown on the image at the top of this post. It would need to be a proper 2-lane road with cycle paths and at least one pavement. Sadly, it would cut through part of the Edenbrook Country Park, but we can think of no other way of directing the extra traffic from 5-10,000 new houses eastbound.

Shapley Heath Major Road Transport Issues: A287

A287

Shapley Heath Major Road Transport Issues: A287

Moving clockwise, the next major road is the A287. The junction with the B3016 Odiham Road is already dangerous. So, there would need to be a new roundabout across the dual carriageway there. The rest of the road is suitable for busy 2-way traffic, but there’s no pavement or cycle path for much of the length of the road. That means this road would need to be widened to accommodate pedestrians and cyclists. And the roundabouts to Odiham and North Warnborough would probably also need to be improved.

M3 Junction

M3 Junction

M3 Junction

Prior studies into a Winchfield new town have raised the possibility of a new motorway junction. This seems unlikely on cost grounds, which means that significant improvements to Junction 5 of the M3 will be required. There is a rudimentary pavement across the junction that can also be used by cyclists, but it is quite dangerous. The pavements on the approach roads are also poor with scant provision for cyclists.

Hook Roundabouts

Hook Roundabouts

Hook Roundabouts

There is little provision for pedestrians on the B3349 from the M3 to Hook and no cycle lane. The roundabout already gets busy so would probably require improvement if Shapley Heath gets built. The other roundabout on Griffin Way South has poor provision for walkers and cyclists and would also need to be improved. Similarly, the roundabout with the A30 would need to be improved, especially as more houses are already being built near there.

Shapley Heath Major Road Transport Issues: A30 London Road

A30 London Road

A30 London Road

The A30 does have a pavement/cycle path between Holt Lane and the turning for Borough Court Road. However, elsewhere the pavement provision is poor. There is room for a cycle path on the dual carriageway part, but not elsewhere. Presumably a new access road will be built to access the Murrell Green part of the development, so a new roundabout across the dual carriageway will be needed.

Hartley Wintney Junctions

Hartley Wintney Junctions

Hartley Wintney Junctions

There are pavements at each of the junctions in Hartley Wintney, but no cycle lanes. However, main road through Hartley wintney gets very busy already, so significant improvements will need to be made at the following junctions:

  • A30/Dilly Lane & Thackham’s Lane
  • A30/B3011 Bracknell Lane
  • A30/A323 Fleet Road

It’s not at all clear if there is enough space to make significant improvements such as adding extra lanes.

Shapley Heath Major Road Transport Issues: A323 Fleet Road

A323 Fleet Road

A323 Fleet Road

It is already almost impossible to turn right out of Church Lane on to Fleet Road, so this junction would need to be improved, perhaps with a roundabout. The stretch of the A323 from Hartley Row Park to the M3 bridge would need widening and improving because it has no pavements and no cycle lane. The junction with Pale Lane would also need to be improved, probably with a roundabout.

 

Are Shapley Heath Sustainable Transport Goals Deliverable?

Shapley Heath Sustainable Transport Goals Overview

Shapley Heath Sustainable Transport Goals Overview

The Shapley Heath Survey has a number of questions about “sustainable transport”. Interestingly, there’s not even an option to request improvement to local roads or to rail services.  When many people think of sustainable transport they think of walking, running and cycling. This can be for fitness, leisure, work or even light shopping.  So, it is worth exploring whether the road network in and around the area of search is capable of delivering the basics such as pavements and cycle paths.

Sadly, the conclusion is a resounding “No”. Overall none of the roads into, out of or through the area of search are capable of sustaining busy 2-way traffic, a pavement on at least one side of the road and even a single cycle lane. Here is the overall assessment, followed by an examination of each road one by one.

Shapley Heath Sustainable Transport Goals Overall Assessment.

Shapley Heath Sustainable Transport Goals Overall Assessment

Having read the rest of this article, you might like to respond to the Shapley Heath survey. This is your chance to make known your concerns about the proposals. We have produced a handy guide with suggestions as to how you might choose to answer the freeform questions. The guide can be found on the download below. The full survey can be found here. The survey closes on 5 July.

Shapley Heath Survey with Suggested Responses
Shapley Heath Survey with Suggested Responses

B3016/Odiham Road

Shapley Heath Sustainable Transport Goals B3016 Odiham Road

Shapley Heath Sustainable Transport Goals B3016 Odiham Road

Starting with the busiest road in the area of search. The B3016/Odiham Road does have a pavement from the A30 to Station Road and this pavement is also designated as a cycle path. There is also a pavement from Bagwell Lane to the A287. However, for the rest of the length of the road, there is no room for either a pavement or a cycle path. There have been fatal accidents on this road, so it is questionable whether it is even suitable to take the extra car traffic from 5-10,000 houses.

Shapley Heath Sustainable Transport Goals: Station Road

Shapley Heath Sustainable Transport Goals Station Road

Shapley Heath Sustainable Transport Goals Station Road

There is a pavement for the short distance from the B3016 to Winchfield Station. The rest of the road is barely capable of taking two way traffic. Of course, there’s a narrow tunnel under the railway too. There is no room for a pavement or cycle path.

Bagwell Lane

Shapley Heath Sustainable Transport Goals Bagwell Lane

Bagwell Lane

The road is barely suitable for occasional 2-way traffic. There’s no pavement and no room for a cycle path along any of its length. There is also a narrow bridge over a water course.

Taplins Farm Lane

Shapley Heath Sustainable Transport Goals Taplins Farm Lane

Taplins Farm Lane

Overall Taplins Farm Lane is barely suitable for 2-way traffic. There is a narrow tunnel under the railway and a blind bend. The bridge over the M3 does have pavements. But there is no pavement anywhere else on the road. There is not enough space for pavements or cycle paths along the rest of the length of the road. When it becomes Church Lane and passes Hartley Wintney it remains a narrow road, with an awkward turning on to the A323.

Shapley Heath Sustainable Transport Goals: Pale Lane

Shapley Heath Sustainable Transport Goals Pale Lane

Shapley Heath Sustainable Transport Goals Pale Lane

Pale Lane is a narrow lane, barely capable of taking occasional 2-way traffic. There is a narrow tunnel under the railway and a narrow bridge over the River Hart. There is no space for a proper 2-way road and no room for pavements or a cycle lane.

Chatter Alley

"Shapley

The road out of the area of search towards Dogmersfield and Crookham Village is Chatter Alley. This is a narrow road with pinch-points to stop 2-way traffic. There is a short stretch of pavement near the school. There is no space for proper 2-way traffic and no room for a cycle lane or pavements along the rest of the length of the road.

Shapley Heath Sustainable Transport Goals: Pilcot Road

Shapley Heath Sustainable Transport Goals Pilcot Road

Pilcot Road

Pilcot Road is another narrow lane with a bridge over the River Hart and a pinch-point to stop 2-way traffic. The stretch up to Crookham Village does have a pavement, but the rest of the road doesn’t and there’s no room for a cycle path.

Totters Lane

"Shapley

This is a narrow road for most of its length and not capable of carrying 2-way traffic. There is also a tight, narrow bridge over the railway. The widest part of the road under the M3 does have a pavement.  However, the rest of the road is not wide enough for a pavement or cycle lane.